# The picks-and-shovels trade is cracking. The build-out is not, yet.

*Data-center construction set a record in September and Caterpillar’s backlog is at a record. At the edges, a buyer wrote off power equipment, two states paused permits and local voters said no. Both sides, and the dated tests.*

By Grant Bishop · Published 16 Nov 2026, 8:06 am ET

The build-out of data centers in the United States has not slowed. Spending on them set a record in September, and Caterpillar, a maker of the engines and turbines that power them, has a record order book. What is cracking is the edge of the trade: a large buyer has taken a $3.7 billion loss after changing its plans for power equipment, two states have paused permits, and local voters turned against new sites almost everywhere they were asked. A boom can set records and still be fragile. This note sets out both.

### Where it stands: the build-out

- **Construction.** Private data-center construction ran at a seasonally adjusted annual rate of $96.5 billion in September, the highest in the Census Bureau's series, which starts in January 2014. A year earlier it was $50.7 billion. In the same month total construction spending fell 1.9% from August, to $2,186.1 billion. [1][2]
- **Equipment.** Caterpillar's sales and revenues were $20.7 billion in the third quarter, up 17% on a year earlier. Sales to power generation customers rose 30%, to $3.4 billion. The company puts the gain mainly down to data centers. [3]
- **Orders.** Caterpillar's backlog was about $78.1 billion at 30 September, $6.0 billion more than three months before. About $32.6 billion of it is not expected to be filled within twelve months. [3]
- **The four big spenders.** Our [House View](/house-view) puts the plans of Amazon, Alphabet, Microsoft and Meta at about $730 billion this year. No cut to those plans has been reported as of the time below. Alphabet said its range of $195 billion to $205 billion is unchanged. [5] Microsoft's figure for calendar 2026 is about $170 billion. Its finance chief tied it on 28 October to delays in capacity from third parties. [4]

### Where it stands: the edges

- **A buyer's write-off.** SoftBank Group booked a loss of ¥597.2 billion ($3.73 billion) in the six months to 30 September. It calls the cause "the realignment of procurement plans for power generation-related equipment" for AI data center projects in the United States. Most of it, ¥457.0 billion, was advance payments it cannot get back. The report does not name the equipment or the suppliers. SoftBank lost ¥1,115.3 billion in July to September, against a profit of ¥2,502.2 billion a year earlier. [6]
- **New York.** An executive order signed on 14 July suspends state permit decisions for data centers that use, or can use, 50 megawatts or more until a statewide environmental review is finished. Applications already judged complete, and local permits, are outside the order. [7]
- **Texas.** On 21 September the governor directed the state's environmental regulator to halt all permits sought by data centers until the grid operator, ERCOT, completes its audit. No calendar date was given. [8]
- **Voters.** According to Ballotpedia, voters favored limiting data-center development in 40 of 41 local ballot measures on 3 November. The results are unofficial until certified. [9]

### The other side, at full strength

The edges may matter less than they look. Spending is at a record, not in retreat. A backlog of $78.1 billion, with $32.6 billion beyond a year, is work already ordered. Pauses are not bans: New York lets complete applications through, and the Texas pause ends with an audit. SoftBank's report also says it is entitled to rebates of up to $2.1 billion over ten years on future equipment purchases. One buyer and 41 local votes are small against $730 billion of planned spending.

The core may also be weaker than the records say. September's construction figure is preliminary and will be revised. A backlog is orders believed firm, and SoftBank's advance payments were firm too, until its plans changed. Microsoft tied its calendar-year figure to late deliveries of outside capacity. Late deliveries are what a stretched supply chain looks like.

And there is the deeper doubt. House View section 3 names the other side of the whole bet: a spending boom with no payoff. Record spending does not answer it. Spending is the cost of the bet. The payoff, if it comes, shows up in output per hour, which is claim 4 of the House View and not yet tested.

This note is context for our only sealed card, [card no. 1 on NVIDIA](/cards/nvda-card-1). It is not a test of that card.

### What would change our answer

Our answer today: cracks at the edges, not yet in the build-out. These dated readings would change it.

- **Tue 1 Dec 2026, 10:00 am ET.** The Census Bureau's October construction spending. [10] A fall in private data-center spending from September's rate, after revision, would be the first sign. Two monthly falls in a row would change our answer.
- **Late January 2027.** Caterpillar's fourth-quarter report. If the backlog is below $78.1 billion while sales still rise, new orders are slowing.
- **The next quarterly reports from Amazon, Alphabet, Microsoft and Meta.** A cut to any one of the four plans is House View watchpoint 3. It would mean the bet is losing nerve.
- **Other buyers.** Whether more buyers of AI infrastructure report cancellations or write-offs like SoftBank's. One is an edge. Several are a pattern.

Data as of 10:55 pm ET, Sun 15 Nov 2026.

## Related

- [Alphabet's shares fell 18% while its sector's profit forecasts rose](https://grantbishop.com/notes/three-stocks-forecasts-2026-11-17)

Sources: https://grantbishop.com/notes/picks-and-shovels/sources (10 sources, with outlet, date and link)

Grant Bishop publishes dated, sealed calls on public companies and grades every one in public. They are the publication's record, not advice to any reader.

Disclosures: https://grantbishop.com/disclosures

Machine-drafted, human-approved.

Corrections: corrections@grantbishop.com